UPDATE 1-Ontario Bruce 1 & 2 reactor restarts delayed

Thu Nov 5, 2009 9:10am GMT
 
Email | Print | | Single Page
[-] Text [+]

(Adds background)

NEW YORK, Nov 4 (Reuters) - TransCanada Corp (TRP.TO) on Wednesday said the return of the 750-megawatt Units 1 and 2 at the Bruce A nuclear power station in Ontario would be delayed until mid 2011 for Unit 2 and about four months later for Unit 1.

Previously, Bruce said the units would return in 2010.

A spokesman at TransCanada, which released its earnings Wednesday, said the company would answer questions about Bruce later this morning on a conference call.

In the earnings release, TransCanada said as of Sept. 30, 2009, Bruce had incurred about C$3.1 billion in costs for the refurbishment of Units 1 and 2 and work was about 75 percent complete.

TransCanada said the delay was mitigated by the previously announced extension of the operating lives of Unit 3 to 2011 and Unit 4 to 2016, with later life extensions expected with additional reactor optimization activities.

The 6,261 MW Bruce station is located in Tiverton on the eastern shore of Lake Huron about 155 miles (250 km) northwest of Toronto. There are four 750 MW units, 1 to 4, at the A station, which entered service in 1977-1979, and three 822 MW units, 5 to 7, and one 795 MW unit, 8, at the B station, which entered service in 1984-1987.

The company expected to increase Unit 8's output to about 822 MW by modifying the fuel-loading system in early 2010.

In the past, Bruce said it planned to spend up to C$3.4 billion to restart Units 1 and 2. Ontario Hydro, the former province-owned power company, shut Unit 1 in 1997 and Unit 2 in 1995 because they needed extensive upgrades.  Continued...

 