Valero plans work on 6 refineries through Nov
NEW YORK, July 29 (Reuters) - Valero Energy Corp. (VLO.N)
said on Tuesday it has scheduled maintenance work at major
processing units in six U.S. oil refineries between July and
November.
Below is a table listing the planned work: REFINERY UNIT BPD MONTH DAYS PORT ARTHUR, TX HYDROCRACKER 45,000 JUL/AUG 38 TEXAS CITY, TX #3 CRUDE UNIT 85,000 SEPT/OCT 35 TEXAS CITY, TX COKER 50,000 SEPT/OCT 40 THREE RIVERS, TX HYDROCRACKER 30,000 SEPT/OCT 28 DELAWARE CITY, DE CRUDE UNIT 180,000 OCT 25 ARDMORE, OK HYDROCRACKER 12,000 OCT/NOV 30 ARDMORE, OK FCC UNIT 30,000 OCT/NOV 20 WILMINGTON, CA FCC UNIT 55,000 OCT/NOV 15
(Reporting by Richard Valdmanis)