PG&E Calif. Diablo Canyon 2 reactor exits refuel
NEW YORK, Nov 11 (Reuters) - PG&E Corp's (PCG.N) 1,118-megawatt Unit 2 at the Diablo Canyon nuclear power plant in California exited a refueling outage and ramped up to 28 percent by early Wednesday, the U.S. Nuclear Regulatory Commission said in a report.
The unit shut by Oct. 5.
It last shut for refueling from about Feb. 3 to April 14, 2008. It is on a 20- to 22-month refueling cycle.
The 2,240-MW Diablo Canyon station is located in Avila Beach in San Luis Obispo County about 195 miles (310 km) northwest of Los Angeles. The station has two units, the 1,122-MW Unit 1 and the 1,118-MW Unit 2, which entered service in 1985 and 1986.
Unit 1 continued to operate at full power.
One MW powers about 700 homes in California.
PG&E, of San Francisco, owns and operates more than 6,200 MW of generating capacity, markets energy commodities, and transmits and distributes electricity to almost 5.3 million customers and natural gas to 4.2 million customers in California. (Reporting by Scott DiSavino; Editing by Lisa Shumaker)
© Thomson Reuters 2009 All rights reserved.