PSEG NJ Salem 2 reactor exits refuel
NEW YORK, Nov 12 (Reuters) - Public Service Enterprise Group Inc's (PEG.N) 1,130-megawatt Unit 2 at the Salem nuclear power station in New Jersey exited a refueling outage and ramped up to 57 percent power by early Thursday from 5 percent early Wednesday, the U.S. Nuclear Regulatory Commission said in a report.
The unit shut by Oct. 14.
The unit last shut for refueling from about March 12 to May 9, 2008. The unit is on an 18-month refueling cycle.
The 3,551 MW Salem/Hope Creek station is located along the Delaware River in Salem, about 40 miles (60 km) south of Philadelphia. There are three reactors at the station, the 1,174 MW Salem 1, which entered service in 1977, 1,130 MW Salem 2 (1981) and the 1,209 MW Hope Creek (1986), and the 38 MW Salem 3 oil-fired turbine.
Salem 1 and Hope Creek continued to operate at full power.
One MW powers about 800 homes in New Jersey.
PSEG operates the station and owns all of Hope Creek and about 57 percent of Salem. Exelon Corp (EXC.N) owns the remaining 43 percent of Salem.
In 2007, PSEG said it planned to spend $50 million between 2007 and 2011 to explore the possible construction of a new reactor at the site. The company planned to file in the spring of 2010 with the NRC to build the new reactor.
In August 2009 PSEG filed with the NRC for 20-year extensions of the original 40-year operating licenses for Hope Creek and both Salem units. The NRC has said it takes about 22 months to make a decision on a license renewal without a hearing and 30 months with a hearing. Continued...