TABLE-U.S. refinery expansion plans (Marathon)
(Marathon update on refinery expansion projects in MI, LA & KY)
REFINERY CAPACITY UNIT COMPLETION
=============================================================================
EAST COAST (PADD 1)
=============================================================================
CONOCOPHILLIPS CORP. (COP.N)
Bayway, NJ 5,800 bpd FCC N/A Revamp, conversion up 4 percent
CDU N/A Revamp
SUNOCO INC. (SUN.N)
Phila., PA 15,000 bpd+ FCC Apr-07 Costs rose from $300 million to
$520 million amid industry-wide
cost pressures and design changes
40-50,000 bpd HDS early-09 up to $275 million to convert an
idle HCU to process heating oil
into ultra-low sulphur diesel VALERO CORP. (VLO.N) Del. City, DE 20,000 bpd CDU N/A Company seeking permits ============================================================================= MIDWEST (PADD 2) ============================================================================= BP PLC (BP.L) Whiting, IN N/A refinery 2011 $3 billion revamp to increase
heavy crude processing, motor
fuels output to rise 55,000 bpd COFFEYVILLE RESOURCES Coffeyville, KS 15,000 bpd CDU late-06 FLINT HILLS RESOURCES Rosemount, MN 50,000 bpd CDU Q4-07
N/A DCU N/A Larger coker drums being installed
FRONTIER OIL CORP. (FTO.N)
El Dorado, KS N/A CDU/VDU Q2-08 $50 million heavy crude revamp
2,500 bpd DCU Q2-08 Two new coker drums
5,000 bpd FCC Q2-09 $78 million expansion
HTU Q2-09 $77 million expansion
MARATHON OIL CORP (MRO.N)
Catlettsburg, KY N/A refinery N/A NOT PURSUED CURRENTLY DUE TO COST
150,000 bpd heavy oil project. Detroit, MI 15,000 bpd refinery 2010 $1.9 bln, expands refinery from
100K to 115K, raise heavy oil
processing by 80K. construction can
start in March or April if air
permit in place, complete late 2010 Robinson, IL N/A refinery N/A NOT PURSUED CURRENTLY DUE TO COST
180,000 bpd heavy oil project.
MURPHY OIL CORP (MUR.N)
Superior, WI N/A refinery N/A Seeking Canadian oil sands partner
for possible expansion SINCLAIR OIL CORP. Tulsa, OK 45,000 bpd refinery 2010 $1 bln, seeking enviro permits SUNOCO Toledo, OH 20,000 bpd CDU Jun-07 $40 million expansion, on budget
10-15,000 bpd HCU end-08 $30 million expansion
20,000 bpd CDU 2008 On hold due to costs
24,000 bpd FCC 2008 On hold due to costs WRB REFINING LLC (ConocoPhillips and EnCana joint venture) Wood River, IL 32,000 bpd GDS 2007 S-Zorb unit
70,000 bpd CDU 2009 CDU, DCU projects are $1.9
65,000 bpd DCU 2009 billion first phase of oil sands
N/A CDU/DCU 2013 Further 100,000 bpd bitumen
$2 billion capital cost WYNNEWOOD REFINING (GARY-WILLIAMS ENERGY) Wynnewood, OK 15,000 bpd CDU Q1-07
20,000 bpd DHT N/A
=============================================================================
GULF COAST (PADD 3)
=============================================================================
CHEVRON CORP. (CVX.N)
Pascagoula, MS 16,000 bpd FCC Late-06 Completed December 2006
14,285 bpd CCR mid 2010 $500 mln, construction
to start in early 2008. Replaces
two older reformers, boosts
gasoline output by 14,285 bpd
200,000 bpd refinery N/A Decision seen 1H 2008. Applied for
permits. Work seen in 2008, 2009
HOLLY CORP. (HOC.N)
Navajo, NM 15,000 bpd CDU Q4-08 revamp
20,000 bpd HCU Q4-08 $240 million total outlay
N/A CDU 2011 40,000 bpd heavy crude revamp
MARATHON OIL CORP. (MRO.N)
Garyville, LA 180,000 bpd CDU Q4-09 $3.2 billion expansion
44,000 bpd DCU Q4-09
70,000 bpd HCU Q4-09
65,000 bpd CCR Q4-09
47,000 bpd KHT Q4-09
MOTIVA ENTERPRISES LLC (RDSa.L)
Pt. Arthur, TX 45,000 bpd DHT 2008 Construction began June 2006
325,000 bpd refinery 2010 $7 bln project approved PASADENA REFINING SYSTEM INC. Pasadena, TX N/A refinery 2010 revamp to run 70,000 bpd Marlim
N/A CDU N/A future 100-200,000 bpd expansion PLACID REFINING COMPANY LLC Port Allen, LA N/A FCC Q2-08 Gasoline output increased 7,000 bpd
N/A CDU Q3-08 Heavy oil revamp
25,000 bpd CDU N/A Planned expansion TOTAL SA (TOTF.PA) Pt. Arthur, TX N/A DCU 2009 $1 billion project studied VALERO ENERGY CORP. (VLO.N) C. Christi, TX N/A ISE Q2-07 MTBE unit conversion Houston, TX N/A HCU Q2-07 Mild hydrocracker Pt. Arthur, TX 75,000 bpd CDU Q1-07 completed and in operation
125,000 bpd refinery 2009 $1.3 billion project, engineering
underway, not yet sanctioned St Charles, LA 45,000 bpd CDU 2010 $1.4 bln, board approved
10,000 bpd coker
50,000 bpd HCU Tx. City, TX 20,000 bpd CDU N/A Expansion canceled on costs
12,000 bpd DCU N/A Expansion canceled on costs WRB REFINING LLC Borger, TX 20,000 bpd DCU Q2-07 Bitumen phase 1, $500 million
debottleneck refinery 2009 Bitumen phase 2, $300 million
54,000 bpd CDU 2012 Bitumen phase 3, $600 million ============================================================================= ROCKY MOUNTAINS (PADD 4) ============================================================================= CONOCOPHILLIPS Billings, MT 10,000 bpd CDU/VDU Q2-07 Heavy crude capacity up 46,000 bpd FRONTIER Cheyenne, WY 4,500 bpd DCU Q3-07 $89 million expansion
N/A CDU Q2-07 $8 million revamp HOLLY Woods Cross, UT 5,000 bpd CDU Q4-08
15,000 bpd HCU Q4-08 $100 million for both projects SINCLAIR Salt Lake, UT 60,000 bpd DCU 2009 Sinclair, WY 20,000 bpd CDU late-06
20,000 bpd DCU late-06 coker purchased from idle refinery ============================================================================= WEST COAST (PADD 5) ============================================================================= BIG WEST OIL LLC Bakersfield, CA 19,200 bpd FCC 2008 $680 million conversion capacity
25,000 bpd DHT 2008 project to double CARB diesel and
9,000 bpd ALK 2008 gasoline output.
CHS INC. (CHSCP.O)
Laurel, MT 15,000 bpd DCU Aug-08 $325 million
CONOCOPHILLIPS
Ferndale, WA 25,000 bpd DCU N/A Adds 25,000 bpd heavy oil capacity
5,000 bpd CDU N/A Rodeo, CA 20,000 bpd HCU
5,000 bpd CDU
Los Angeles N/A DCU N/A/ Revamp, clean yields up 2 percent
TESORO CORP. (TSO.N)
Los Angeles N/A DCU N/A revamp
N/A DHT N/A revamp Martinez, CA N/A DCU N/A Conversion of existing fluid
coker,costs as high as $525
million from $275 million initial
estimate Anacortes, WA 25,000 bpd DCU cancelled July 2006 on costs
N/A refinery H2-07
$34 million sour crude revamp VALERO Benicia, CA N/A DHT Q3-07 ULSD unit, $105 million Wilmington, CA N/A ALK Q4-07 $195 million project ============================================================================= PERMITS PENDING MARATHON
Canton, OH Diesel hydrotreater waiting for air permits MOTIVA
Norco, LA Modification of hydrocracking unit Feb 7 2008 KEY: FCC: Fluid Catalytic Cracker; CDU: Crude Distillation Unit; VDU: Vacuum Distillation Unit; DCU: Delayed Coker Unit; DHT: Distillate Hydrotreater; HTU: Hydrotreater; HCU: Hydrocracker; CCR: Catalytic Reformer; KHT: Kerosene Hydrotreater; GDS: Gasoline Desulphurization Unit; ALK: Alkylation unit ISE: Iso-Octene unit
© Thomson Reuters 2009 All rights reserved.