TABLE-Swiss nuclear plant outages and restarts

 (Introduces 2020 schedules)
    Dec 4 (Reuters) - The following table lists maintenance outages, unscheduled stoppages and
load reductions at Swiss nuclear power plants.

Maintenance usually takes place in the spring and summer.

Ownership of the plants is detailed under (1,2,3...)
    
Please click on the link at the bottom to access the data.
    
 New content ***


    
                                                                               
 REACTOR NAME               CAPACITY (MW)           TIME PERIOD                OPERATOR
                                                                               
 PLANNED OUTAGES/LOAD                                                          
 DROPS 2020                                                                    
 Leibstadt                  1,245                   May 4-Aug 9                Alpiq (3)
 Goesgen                    1,010                   May 23-Jun 26              Alpiq (2)
 Beznau 1                   365                     Apr 17-May 22              Axpo (1)
 Beznau 2                   365                     Aug 4-16                   Axpo (1)
                                                                               
 ONGOING AND PLANNED                                                           
 OUTAGES/LOAD DROPS 2019                                                       
 Leibstadt                  1,245                   open                       Alpiq (3)
 Goesgen                    1,010                   open                       Alpiq (2)
 Muehleberg                 355                     closes permanentaly at     BKW-FMB (4)
                                                    the end of 2019            
 Beznau 1                   365                     open                       Axpo (1)
 Beznau 2                   365                     open                       Axpo (1)
                                                                               
 COMPLETED OUTAGES, LOAD                                                       
 CUTS IN 2019                                                                  
 Muehleberg                 355                     Cuts by 24 MW on Jan       BKW-FMB (4)
                                                    24/25 for 12.5 hrs, cuts   
                                                    by 67 MW for 2 hrs on Jan  
                                                    28, Mar 14, 56 MW drop     
                                                    for 1 3/4 hrs, Apr 11,     
                                                    May 16, Jun 13, Jul 18,    
                                                    Aug 15, Sep 5, 12, 19,     
                                                    26, Oct 24                 
 Goesgen                    1,010                   Intraday cuts on Feb 2,    Alpiq (2)
                                                    4-5, Jun 1-22, Jul 26-Aug  
                                                    11                         
 Leibstadt                  1,245                   Feb 6: 4 hr standstill,    Alpiq (3)
                                                    Jan 19 1 hr cut by 345     
                                                    MW, Nov 2-Mar 19, load     
                                                    cuts by 130 MW, Apr 25     
                                                    fully off for several      
                                                    hours, Mar 19-Apr 24 load  
                                                    cuts by 110 MW, Apr 24-26  
                                                    fully off, cuts by 110 MW  
                                                    to May 12, fully off May   
                                                    12-15, to shed 110 MW up   
                                                    to Jun 3, Jun 3-Jul 8,     
                                                    Sep 23, 28, Nov 23, 1 hr   
                                                    cut by 340 MW              
 Beznau 1                   365                     May 3-Jun 9/10, several    Axpo (1)
                                                    hours offline on Aug 6     
                                                    after overnight            
                                                    thunderstorm               
 Beznau 2                   365                     Aug 10-Sep 20              Axpo (1)
 Source: here availability/
here
    
1) Axpo AG (formlery NOK) is part of the Axpo Holding which is 100% in public hands and also
consists of Centralschweizerische Kraftwerke AG (CKW) and EGL AG.

2) Alpiq (40%), Axpo (25%), Zurich city (15%), CKW (12.5%), Energie Wasser Bern (ewb) (7.5%)

3) KKL is the operator, of which Alpiq AG (27.4%), Alpiq Suisse SA (5%), Axpo AG (22.8%), EGL AG
(16.3%), CKW (13.6%), BKW FMB Beteiligungen AG (9.5%), AEW Energie AG (5.4%)

4) Canton Berne (52.54%), EAG (10%), E.ON Energie (7.03%), BKW FMB (9.99%), others (20.44%)

 (Reporting by Vera Eckert in Frankfurt)
  
0 : 0
  • narrow-browser-and-phone
  • medium-browser-and-portrait-tablet
  • landscape-tablet
  • medium-wide-browser
  • wide-browser-and-larger
  • medium-browser-and-landscape-tablet
  • medium-wide-browser-and-larger
  • above-phone
  • portrait-tablet-and-above
  • above-portrait-tablet
  • landscape-tablet-and-above
  • landscape-tablet-and-medium-wide-browser
  • portrait-tablet-and-below
  • landscape-tablet-and-below